Migration from the old CVCOG building to the new CVCOG building located here. Phase 1:
- Install (12) UniFi network switches in existing 2 post relay racks, patch in existing patch panels with existing patch cables. Label switch ports in UniFi controller to match patch panels.
- Install (6) UniFi AC HD's to replace existing Cisco AP's. Adopt and configure appropriately.
- Install (1) new 2-post relay rack for phone, video surveillance, and other miscellaneous equipment.
- Install (2) CyberPower UPS's at the bottom of the new relay rack - Configure SMTP and email alerts.
- Install (3) Automated Transfer Switch PDU's, one for each relay rack to tie them into the 2 separate UPS's. Configure SMTP and email alerts.
- Install (1) Sophos XG router. Setup DHCP on the XG.
- Activate Suddenlink fiber and turn-up once installed.
- Physically move (2) network cabinets, ~15 physical servers, and existing UPS's to the new location.
- Update IP scheme, DNS, and any necessary AD objects on all physical/virtual servers to fit new IP Scheme. Update DHCP scopes to match new subnets etc.
- Move PBX to new location and ensure phone operation at old location. This will entail pushing provisioning changes out to those phones to register with the new PBX IP.
- Activate Suddenlink SIP service at this time and cancel old SIP service at old location after the port.